Progress of the one-stop centre project

PKKI STAFF VISIT TO THE SITE AFTER RECEIVING THE TITLE TO THE PIECE OF LAND FROM THE LAND OFFICE IN FEBRUARY 2020.

Onestop-Centre-Project-1 Onestop-Centre-Project-2

4TH AUGUST 2023 – NOTICES WERE PLACED AT THE CAR-PORCHES (WHICH WERE BUILT ON PKKI LAND) AND ALSO DISTRIBUTED TO THE RESIDENTS OF THE ROW OF TERRANCE HOUSES FACING PKKI PROJECT SITE INFORMING THEM THAT A 3-STOREY TRAINING & REHABILITATION CENTRE FOR SPECIAL CHILDREN WITH PHYSICAL AND MENTAL DISABILITIES WILL BE BUILT ON LOT 7243, AND AN OPERATION TO CLEAR ALL STRUCTURES (CAR GARAGE AND PLANTS) WILL BE CARRIED OUT ON 21ST AUGUST 2023.

NOTICES-WERE-PLACED-AT-THE-CAR

24TH AUGUST 2023 – SURVEYOR FROM JURUKUR JITU RUNDING AT THE PROJECT SITE TO DO DEMARCATION SURVEY FOR LOT 7243 JALAN KEMACAHAYA.

SURVEYOR-FROM-JURUKUR-JITU-RUNDING

28TH AUGUST 2023 – PROCEED TO DO THE BOUNDARY PEGGING OF THE PROJECT SITE. COMPLETED BOUNDARY FOR 6 KEY POINTS AND THE OFFICIAL DEMARCATION PLAN.

PROCEED-TO-DO-THE-BOUNDARY-PEGGING

5TH SEPTEMBER 2023 – START DILAPIDATION SURVEY ON SURROUNDING NEIGHBOUR AND ROAD AREA.

START-DILAPIDATION-SURVEY

6TH SEPTEMBER 2023 – ARRIVAL OF EXCAVATOR AT PROJECT SITE.

ARRIVAL-OF-EXCAVATOR-AT-PROJECT-SITE

6TH SEPTEMBER 2023 – COMMERCE SITE CLEARING WORK.

COMMERCE-SITE-CLEARING-WORK

7TH SEPTEMBER 2023 – NEIGHBOUR RESIDENTS DIMANTLED THEIR CARPORCH.

NEIGHBOUR-RESIDENTS-DIMANTLED-THEIR-CARPORCH

11TH SEPTEMBER 2023 – SURVEYOR AT THE CLEARED SITE CONFIRMING THE DEMARCATION.

SURVEYOR-AT-THE-CLEARED-SITE-CONFIRMING-THE-DEMARCATION

12TH SEPTEMBER 2023 – INSTALLATION OF HOARDING.

INSTALLATION-OF-HOARDING

23RD SEPTEMBER 2023 – SURVEYOR AT SITE PEGGING THE PILING POINTS.

SURVEYOR-AT-SITE-PEGGING-THE-PILING-POINTS

23RD SEPTEMBER 2023 – ARRIVAL OF PILING MACHINE AT PROJECT SITE.

ARRIVAL-OF-PILING-MACHINE-AT-PROJECT-SITE

25TH SEPTEMBER 2023 – COMMENCEMENT OF PILING WORKS.

COMMENCEMENT-OF-PILING-WORKS

26TH SEPTEMBER 2023 – INSTALLATION OF PROJECT SIGNBOARD.

INSTALLATION-OF-PROJECT-SIGNBOARD

26TH SEPTEMBER 2023 – PILING WORKS IN PROGRESS.

PILING-WORKS-IN-PROGRESS

26TH SEPTEMBER 2023 – EXCAVATION OF RC WALL IN PROGRESS.

EXCAVATION-OF-RC-WALL-IN-PROGRESS

3RD OCTOBER 2023 – COMMERCE WORK FOR RC WALL.

COMMERCE-WORK-FOR-RC-WALL

7TH OCTOBER 2023 – CASTING OF RC WALL.

CASTING-OF-RC-WALL

16TH DECEMBER 2023 – APPLYING WATER PROOFING FOR INNER LIFT WALL

1116-progress1

18TH DECEMBER 2023 – PILLING WORK HAS BEEN COMPLETED

1116-progress2 1116-progress3

22ND DECEMBER 2023 – SITE INSPECTION FOR COMPLETION OF PILLING WORK

1116-progress4

Phase Two – Building Contruction of The One-Stop Centre Project

BMC Legend Builder Sdn Bhd has been awarded the phrase two building and construction work for  RM3,959,580.00 which will begin in the month of May 2024.